Industrial Building Conversions

We are looking for a small office building to buyof which will need to be approved by the local
for our professional practice. Our broker isjurisdiction. But this is relatively minor compared to
suggesting that we buy an industrial building andthe time and expense of a change of zoning, or
convert it to an office building. Is this practical?obtaining a special use permit.
As property values have risen on Long Island,The surrounding properties are also a
particularly in Nassau County, the highest and bestconsideration. I would have little concern about an
use of properties has often changed. So aoffice conversion if the property were located in
well-placed industrial building may indeed be awell-maintained industrial and research park. But
candidate for conversion. And it may also be athe resale value of your office conversion may
pitfall for the unwary! So let's take a look atbe a problem if it is located next to heavy
some of the factors involved in a conversion andindustrial manufacturing or a scrap yard!
how practical it may be.Know your construction costs before committing
One the first concerns I have is parking. Manyto the project! These costs are highly dependent
older industrial buildings were legally built with aon the actual structure you are considering, so
parking ratio of "two to one." This means thatavoid averages or "ball-park" conversion
there were two parking spaces allocated forestimates. You cannot afford to negotiate on the
every 1,000 square feet of building area. Thisexisting building without knowing your total cost,
would be woefully inadequate for any sort ofwhich includes acquisition, conversion, and soft
office use, and would not meet any moderncosts.
building code for office use. An office building isTwo other quick caveats: The industrial building will
often required to have a parking ratio of five tohave taxes that seem low by office standards -
one, and sometimes more. So in mostthat will change when the building is assessed! And
jurisdictions, a 10,000 square foot office buildingdon't forget to factor in the time and effort that
would need at least 50 parking spaces. So theit will take to supervise, or live through the
office conversion candidate probably needs anconversion process. A typical industrial conversion
oversize plot, or an adjoining plot that may bewould probably take no less than six months, and
acquired. Or, the economics may actually justifycould certainly take up to year including filing and
demolishing part of the existing structure toapprovals.
create additional parking.Properly done, an industrial conversion can be
Zoning in many areas actually allows officeoutstanding buy, and I can point to many
buildings to be built in an industrial zone, "as ofexamples on Long Island. But the process requires
right", meaning that a zoning variance will not beexhaustive research, which is best done by an
required for a conversion. But this is notarchitect whom you have hired long before you
necessarily so. The actual conversion will requirego to contract!
building plans, and probably a new site plan, both